skip top site navigation
News
City of Kaukauna

Project 1-23 Concrete Street Paving Project – Week of November 6th

Posted on Nov 3, 2023 by

See below for a weekly construction update for the Concrete Street Paving Project. Click here for a project map.

Quinney Avenue, Metoxen Avenue, Dixon Street and Seventh Street Areas:

CONSTRUCTION – The grading and backfilling behind the curb and landscaping should be finished early the week of November 6th.

Loderbauer Road, White Dove Lane and White Birch Lane Areas:

CONSTRUCTION – The project is complete.

Greyhound Street, Boxer Street and Setter Drive Areas:

CONSTRUCTION – The project is complete.

Oak Street and Schultheis Street Areas:

CONSTRUCTION -The contractor has completed the concrete street work.  The sidewalk and driveway apron replacement and construction will start the week of November 6th.

Canal Street Area:

CONSTRUCTION – The contractor has completed the concrete street work.  The sidewalk and driveway apron replacement and construction will start the week of November 6th.

Posted in Engineering | Comments Off on Project 1-23 Concrete Street Paving Project – Week of November 6th