Project 1-23 Concrete Street Paving Project – Week of July 10th

Posted on Jul 7, 2023 by

See below for a weekly construction update for the Concrete Street Paving Project. Click here for project maps.

Quinney Avenue, Metoxen Avenue, Dixon Street and Seventh Street Areas:

CONSTRUCTION – The storm sewer contractor continues working on the storm sewer relaying along Seventh Street.  The contractor will start storm sewer work on Metoxen Avenue next week.  Then work on storm sewer lateral installation after the storm sewer mains have been installed.

If you have a driveway along Seventh Street or Metoxen, please find alternate while the sewer crew is working in front of your lot . They should have all driveways open to residents at the end of the workday.

The paving contractor plans to start pavement removal and excavation work the week of July 17th.  When the paving contractor sends an updated schedule, an update will be sent.

Loderbauer Road, White Dove Lane and White Birch Lane Areas:

CONSTRUCTION -The Paving contractor is planning to start removing existing pavement and excavating the existing stone base on Loderbauer Road on July 10th. The contractor will then place base stone and grade the stone. This section of Loderbauer will be closed to traffic during this work. The contractor is looking to pave the first lane of White Dove and White Birch sometime early the week of July 10th. While the contractor is paving White Birch and White Dove, you will not be able to drive on these streets. You will not be able to drive on the new concrete for 7 days while it is curing and strengthening.

–  The contractor will grade and pave the other lane once the first lane has cured and strengthened.

Greyhound Street, Boxer Street and Setter Drive Areas:

CONSTRUCTION – The first lane of concrete pavement should be done on Friday July 7th. You will not be able to drive on the new concrete for 7 days while it is curing and strengthening.  The second lane of concrete will be graded and paved once the first lane has strengthened the 7 days.

Oak Street and Schultheis Street Areas:

CONSTRUCTION -The storm sewer contractor is planning to start storm sewer work the week of July 17th.  The paving contractor plans to start pavement removal and excavation work the week of August 14th. When the paving contractor sends an updated schedule, an update will be sent.

Canal Street Area:

CONSTRUCTION – The storm sewer contractor is planning to start storm sewer work the week of July 24th.  The paving contractor plans to start pavement removal and excavation work the week of August 21st.  When the paving contractor sends an updated schedule, an update will be sent.