Project 2-23 Update – Week of October 23rd
Click here for proposed work locations and possible residence impacts for the week of October 23rd.
Park Street, Klein Street, 4th Street, & 5th Street Areas:
CONSTRUCTION :
- Scott Lamers will continue their work on private sanitary sewer laterals and water services throughout the job site.
- Northeast Asphalt will be back on site Monday, October 23rd. They will be milling the remaining areas that need to be paved. Paving will not happen until the week of October 30th. They will smooth the roadway out for travel, and ramp any areas that need to be for ease of driving until they come back to place asphalt.
DRIVEWAYS/PARKING – Please do not park on Park Street, Sullivan Avenue, Klein Street, 5th Street, or Hendricks Avenue while the Contractor is performing their milling work. They need plenty of room for their trucks and equipment to be able to easily and quickly complete their respective work. Park in your driveway if possible, or far enough away from their work zones.
- If you need special accommodations for parking, please reach out as we can arrange different parking options. This includes anyone with disabilities, recent surgeries, expecting mothers, and mothers with newborns that have appointments. Unfortunately, there is no “one size fits all” for parking and property access. The fewer cars that the contractor has to work around, the faster they can get the work done on your block and move on.
WORK ZONE SAFETY
While driving through the construction site, be sure to travel slowly and keep an eye out for equipment. This not only cuts down on dust, but also keeps the construction workers safe. Operators try their best to see traffic, but their view can be obstructed at times. It is always best to try and gain eye contact with equipment operators prior to driving by. You may need to wait at times before driving by depending on the work being performed. Please be patient during construction.
*PLEASE NOTE THAT THIS WORK AND SCHEDULE CAN CHANGE DUE TO WEATHER OR UNFORSEEN CONSTRUCTION DELAYS. THESE UPDATES ARE TO AID THE COMMUNICATION PROCESS AS WE ALL WORK TOGETHER TO COMPLETE THIS PROJECT IN A TIMELY MANNER*
Utility and Street Construction is not easy. There will be dirt, mud, dust, equipment, and workers everywhere. Construction activity will be noisy, and getting to your residence will be difficult at times. We understand that it can be frustrating while it happens, but we ask for your patience and understanding as we make the much needed improvements to your street and utilities. Please do not hesitate to contact us with any questions or concerns. We can’t help if we don’t know.