See below for a weekly construction update for the Concrete Street Paving Project. Click here for project maps.

Quinney Avenue, Metoxen Avenue, Dixon Street and Seventh Street Areas:

CONSTRUCTION – The storm sewer contractor is currently working on the storm sewer laterals along Dixon Street.  They will continue working on Dixon on Monday.  Tuesday the contractor may be starting the storm sewer in Seventh Street at Metoxen Avenue and working towards Crooks.

If you have a driveway along Seventh Street, please find alternate while the sewer crew is working in front of your lot . They should have all drivees open to residents at the end of the workday.

The paving contractor plans to start pavement removal and excavation work the week of July 24th.  This date was moved back again due to the contractor’s schedule. When the paving contractor has a set updated schedule, another update will be sent.

Loderbauer Road, White Dove Lane and White Birch Lane Areas:

CONSTRUCTION -The paving contractor plans to start pavement removal and excavation work on Loderbauer Road the week of July 17th.  The paving contractor will start grading White Birch Land and White Dove Lane the week of July 24th.  This date was moved back again due to the contractor’s schedule. When the paving contractor has a set updated schedule, another update will be sent.

Greyhound Street, Boxer Street and Setter Drive Areas:

CONSTRUCTION – The paving contractor will start grading Greyhound Street, Boxer Street and Setter Drive the week of July 5th. This date was moved back again due to the contractor’s schedule. When the paving contractor has a set updated schedule, another update will be sent.

Oak Street and Schultheis Street Areas:

CONSTRUCTION -The storm sewer contractor is planning to start storm sewer work the week of July 10rd.  The paving contractor plans to start pavement removal and excavation work the week of August 14th. This date was moved back again due to the contractor’s schedule. When the paving contractor has a set updated schedule, another update will be sent.

Canal Street Area:

CONSTRUCTION – The storm sewer contractor is planning to start storm sewer work the week of July 17th.  The paving contractor plans to start pavement removal and excavation work the week of August 21st.  This date was moved back again due to the contractor’s schedule. When the paving contractor has a set updated schedule, another update will be sent.