Road Construction Updates – Week of Sept. 30 – Oct. 4

Posted on Sep 27, 2024 by

1-24 Concrete Street Paving Project

The contractor will finish working on sidewalk, driveway apron and alley apron replacement the week of September 30th.  The contractor will let area residents know when they will be replacing their sidewalk apron and/or the sidewalk across their driveway.  Residents will need to find an alternative parking spot for roughly 7 days while this concrete cures and strengthens.

  • The landscape contractor will continue to backfill, grade, seed, and place erosion mat on the terraces the week of September 30th.  Please water the new landscaping to help the new grass to grow.

Schedule could change due to weather or Contractor’s other project obligations.

 

3-24 Concrete Alley Paving Project

The contractor will continue working on the pedestrian alleys the week of September 30th.  This concrete will have a design representing the river.  The concrete work in the pedestrian alleys will take longer due to the integrate concrete forming and detail work.

  • The soil and planter wall caps will be installed after the concrete in the pedestrian alleys is complete and has had time to strengthen and cure.
  • The main Second/Third Street Alley will be closed where the pedestrian alleys intersect. The main alley in this location will be closed to traffic for 7 days after the last concrete pour.
  • The contractor will also be replacing some of the sidewalk and alley aprons at the ends of the alleys.  They will do this work in phases to keep at least one end of the each alley open for traffic.