See below for a weekly construction update for the Concrete Street Paving Project. Click here for a project map.

Quinney Avenue, Metoxen Avenue, Dixon Street and Seventh Street Areas:

CONSTRUCTION – The storm sewer contractor will be finishing up the storm sewer work for this area by the end of Tuesday.

The paving contractor will continue pavement removal, excavation and stone placement work the week of August 7th on Dixon Street.  The contractor will then start on Metoxen Avenue and they might start Seventh Street.

If you have a driveway along Dixon Street, Metoxen or possibly Seventh Street, please find alternate while the sewer crew is working in front of your lot .

CROOKS AVENUE/4TH STREET INTERSECTION CLOSURE:

See page 2 of the work map for details related to the closure of the Crooks/4th Intersection outside lanes. The anticipated work schedule is as follows (same as last week’s update):

  • Friday, August 4th – On Friday, Barricades will be placed in Crooks Avenue at the 4th Street Intersection. These barricades will block the outside travel lanes while the road is saw cut in anticipation for work taking place the following week. Upon completion of sawing, road will be cleaned, and barricades will be removed from the street for the weekend, leaving it open to traffic.
  • Saturday & Sunday, August 5th & 6th – Road Open to Traffic for the weekend.
  • Monday & Tuesday, August 7th & 8th – Barricades will be reinstalled as shown in the drawings first thing Monday Morning. The Sewer Contractor will then begin removing concrete and excavating for the work they need to complete. They will work on this Monday and Tuesday.
  • Wednesday, August 9th – The Concrete Contractor should be on site to grade, prep, and pour the roadways back in place. This concrete should cure in 24-36 hours.
  • Friday, August 11th – When the new concrete has reached its desired strength, barrels and barricades will be removed from the intersection and it will be opened to traffic.

WORK ZONE SAFETY – While driving through the construction site, be sure to travel slowly and keep an eye out for equipment. This not only cuts down on dust, but also keeps the construction workers safe. Operators try their best to see traffic, but their view can be obstructed at times. It is always best to try and gain eye contact with equipment operators prior to driving by. You may need to wait at times before driving by depending on the work being performed. Please be patient during construction.

Loderbauer Road, White Dove Lane and White Birch Lane Areas:

CONSTRUCTION – This week the contractor will be paving the west lane of Loderbauer Road. This lane will be closed to traffic for about 7 days for the concrete to cure and strengthen.

The sidewalk contractor will continue constructing the sidewalks and driveway aprons along White Dove and White Birch the week of August 7th. You will not be able to get into your driveway for 7 days after the sidewalk contractor constructs your driveway apron and the sidewalk that goes across your driveway.  You can continue to park at the northern portion of White Birch and Red Fox Lane while your driveway apron and sidewalk cure and harden.

Shortly after the sidewalk and driveway aprons are complete, the landscaper should start the landscape work.

Greyhound Street, Boxer Street and Setter Drive Areas:

CONSTRUCTION – The sidewalk contractor continues constructing the sidewalks and driveway aprons along Greyhound, Boxer and Setter Drive. They will continue to work on the sidewalk and aprons the week of August 7th.  You will not be able to get into your driveway for 7 days after the sidewalk contractor constructs your driveway apron and the sidewalk that goes across your driveway.  You can continue to park at the northern portion of White Birch and Red Fox Lane while your driveway apron and sidewalk cure and harden.

Shortly after the sidewalk and driveway aprons are complete, the landscaper should start the landscape work.

The concrete street contractor will be pouring some street at the intersection of Setter and Greyhound.  You will not be able to drive on this concrete for Seven days while it hardens.

Oak Street and Schultheis Street Areas:

CONSTRUCTION -The storm sewer contractor is planning to start storm sewer work the later the week of August 7th.  The paving contractor plans to start pavement removal and excavation work the week of August 21st.

Canal Street Area:

CONSTRUCTION – The storm sewer contractor is planning to start storm sewer work the week of August 21st.  The paving contractor plans to start pavement removal and excavation work the week of August 28th .

Currently the Water Department’s contractor is boring a water main under the navigation canal. This should take about 2 weeks to complete. Once this work is complete, the water main contractor will relay the water main in Canal Street.

When the paving contractor sends an updated schedule, I will send out another update