Project 2-23 Update – Week of 08/07

Posted on Aug 4, 2023 by

Click here for proposed work locations and possible residence impacts for the week of August 7th.

Park Street, Klein Street, 4th Street, & 5th Street Areas:

CONSTRUCTION – Scott Lamers will continue working on 5th Street next week with Private Sanitary Laterals and Water Services.

Carl Bowers will be on site Monday to begin working at the Crooks/4th Intersection. By Wednesday they should be working their way northwest    along 4th Street as they construct the new water main.

Al Dix will be at the Crooks/4th Street intersection replacing concrete on Wednesday & Thursday.

DRIVEWAYS/PARKING – Please do not park on the Road on 4th Street or 5th Street while the contractors are performing their work. They need plenty of room for their trucks and equipment to be able to easily and quickly complete their respective work. Park in your driveway if possible, or on the nearest side street.

  • If you need special accommodations for parking, please reach out as we can arrange different parking options. This includes anyone with disabilities, recent surgeries, expecting mothers, and mothers with newborns that have appointments. Unfortunately, there is no “one size fits all” for parking and property access. The fewer cars that the contractor has to work around, the faster they can get the work done on your block and move on.

Crooks Avenue/4th Street Intersection Closure:

See page 2 of the work map for details related to the closure of the Crooks/4th Intersection outside lanes. The anticipated work schedule is as follows (same as last week’s update):

  • Friday, August 4th – On Friday, Barricades will be placed in Crooks Avenue at the 4th Street Intersection. These barricades will block the outside travel lanes while the road is saw cut in anticipation for work taking place the following week. Upon completion of sawing, road will be cleaned, and barricades will be removed from the street for the weekend, leaving it open to traffic.
  • Saturday & Sunday, August 5th & 6th – Road Open to Traffic for the weekend.
  • Monday & Tuesday, August 7th & 8th – Barricades will be reinstalled as shown in the drawings first thing Monday Morning. The Sewer Contractor will then begin removing concrete and excavating for the work they need to complete. They will work on this Monday and Tuesday.
  • Wednesday, August 9th – The Concrete Contractor should be on site to grade, prep, and pour the roadways back in place. This concrete should cure in 24-36 hours.
  • Friday, August 11th – When the new concrete has reached its desired strength, barrels and barricades will be removed from the intersection and it will be opened to traffic.

WORK ZONE SAFETY

While driving through the construction site, be sure to travel slowly and keep an eye out for equipment. This not only cuts down on dust, but also keeps the construction workers safe. Operators try their best to see traffic, but their view can be obstructed at times. It is always best to try and gain eye contact with equipment operators prior to driving by. You may need to wait at times before driving by depending on the work being performed. Please be patient during construction.

*PLEASE NOTE THAT THIS WORK AND SCHEDULE CAN CHANGE DUE TO WEATHER OR UNFORSEEN CONSTRUCTION DELAYS. THESE UPDATES ARE TO AID THE COMMUNICATION PROCESS AS WE ALL WORK TOGETHER TO COMPLETE THIS PROJECT IN A TIMELY MANNER*

Utility and Street Construction is not easy. There will be dirt, mud, dust, equipment, and workers everywhere. Construction activity will be noisy, and getting to your residence will be difficult at times. We understand that it can be frustrating while it happens, but we ask for your patience and understanding as we make the much needed improvements to your street and utilities. Please do not hesitate to contact us with any questions or concerns. We can’t help if we don’t know.