Construction Updates for the week of August 25-29

Andrea Fencl
August 22, 2025

2-25 Tobacnoir Area Utility Relay

  • Carl Bowers ConstructionWill have 2 crews on site working in separate locations:
    • Crew 1 – Will be working on constructing new Water Mains and Sanitary Sewer Mains on Ducharme Street between Lawe and Oviatt, and on Oviatt Street between Tobacnoir and Seymour. The anticipated work path would be working from north to south in each block.
    • Crew 2 – Will be working on Sanitary Sewer Laterals and Water Services between the main lines in the roadway up to the back of sidewalk on Desnoyer Street between Tobacnoir and Seymour.

Map showing work to be done on Desnoyer Street and Oviatt Street from Tobacnoir Street to Seymour Street. Some work will also be done on Ducharme Street from Lawe Street to Oviatt Street.

General Notes

DRIVEWAYS/PARKING – Please do not park on the road while the contractor is performing their work in the area. They need plenty of room for their trucks and equipment to be able to easily, quickly, and safely complete their work. Park in your driveway if possible, or on the nearest side street.

  • If you need special accommodations for parking, please reach out as we can arrange different parking options. This includes anyone with disabilities, recent surgeries, expecting mothers, and mothers with newborns that have appointments. Unfortunately, there is no “one size fits all” for parking and property access. The fewer cars that the contractor has to work around, the faster they can get the work done on your block and move on.

WORK ZONE SAFETY – While driving through the construction site, be sure to travel slowly and keep an eye out for equipment. This not only cuts down on dust, but also keeps the construction workers safe. Operators try their best to see traffic, but their view can be obstructed at times. It is always best to try and gain eye contact with equipment operators prior to driving by. You may need to wait at times before driving by depending on the work being performed. Please be patient during construction.

*  PLEASE NOTE THAT THIS WORK AND SCHEDULE CAN CHANGE DUE TO WEATHER OR UNFORSEEN CONSTRUCTION DELAYS. THESE UPDATES ARE TO AID THE COMMUNICATION PROCESS AS WE ALL WORK TOGETHER TO COMPLETE THIS PROJECT IN A TIMELY MANNER  *

Utility and Street Construction is not easy. There will be dirt, mud, dust, equipment, and workers everywhere. Construction activity will be noisy, and getting to your residence will be difficult at times. We understand that it can be frustrating while it happens, but we ask for your patience and understanding as we make the much needed improvements to your street and utilities. Please do not hesitate to contact our Engineering Department with any questions or concerns. We can’t help if we don’t know.

Article Author