2025 Road Construction Updates – 9-25 Linda Court & Thelen Avenue Utility Relay Update

Andrea Fencl
July 25, 2025

Utility work in the roadway has been completed! There should not be much for activity next week on site. USPS was contacted a few days ago to resume mail delivery.

CONSTRUCTION:

  • Carl Bowers ConstructionFinished with Utility Construction in the roadway.
  • Northeast Asphalt – Is tentatively scheduled to come to the job site around August 11th to prep and place asphalt pavement on all disturbed, previously paved areas. An update will be sent out closer to that time with more details.
  • Scott Lamers Construction – Still waiting on a firm schedule from Scott Lamers Construction to come to the job site to perform private sewer and/or water service replacement. An update will be sent out closer to that time with more details.