2025 Road Construction Updates – 1-25 Concrete Street Paving Project July 21-25

The contractor will be excavating for sidewalk and driveway aprons next week. The contractor will be starting on the side of the street that was paved last. Below is the order in which the contractor will be excavating the street and side for sidewalk and driveway aprons.
- Weiler Road – west side (this Friday)
- Weiler Road – east side (possibly this Friday or Monday)
- Beckett Lane -west side (Monday)
- Becket Road – east side (Monday)
- Antelope Trail – north side (Tuesday and Wednesday)
- Antelope Trial – south side (Tuesday and Wednesday)
The sidewalk/driveway apron contractor will be constructing sidewalk shortly after the sidewalk excavation. Please stay off newly poured concrete for 7 days or until the contractor has removed all barricades. For garbage pick up, please set out your garbage and recycling like usual.
The asphalt paving of the intersection of Ash Grove and State Street will take place in early August.