CONSTRUCTION – The contractor gave me their schedule for the end of this week and the week of June 2nd .

  • The contractor has finished the sidewalk and driveway apron on Ash Grove Place this week.  They will continue to work on the State Street sidewalk next week.
  • The contractor will be finishing the sidewalk and driveway apron construction tomorrow or early next week on White Dove Lane and White Wolf Lane.
  • The contractor will be placing stone for sidewalk and driveway aprons along Bear Paw early the week of June 2nd.   The contractor will be constructing the sidewalk and driveway aprons along Bear Paw later the week of June 2nd.  The contractor will be start the excavation and stone placement for sidewalk on Snow Goose next week and maybe start construction of the sidewalk later next week.
  • You can currently park your vehicles on the street in front of your property.  When the contractor is working on the sidewalk work on your street, you will need to park somewhere else between the hours of 7:00 AM and 6:00 PM.
  • The construction schedule may change due to weather or contracts other obligations.