2025 Road Construction Updates – 1-25 Concrete Street Paving Project May 12-16

CONSTRUCTION – Below is the tentative schedule up to the week of May 12.
- May 9
- Pave 2nd sides – Friday
- Ashgrove Pl-East Side
- Bear Paw Trail – south side
- Might pave north side of Campfire
- Pave 2nd sides – Friday
- Week of May 12
- Pave 2nd sides – Monday
- Snow Goose Way-West side
- White Dove Ln- North side
- Campfire Ct-North side
- White Wolf Lane-South Side
- Pave 2nd sides – Monday
- Parking for Phase 1 of the Paving Project
- Weiler Road
- Antelope Trial
- Haas Road
- Beckett Lane
- White Birch Trail
- Hennes Court
- The sidewalk and driveway apron work will start the week of May 19th. Please email mail if you have any concerns about sidewalk or driveway apron construction. The construction schedule may change due to weather or contracts other obligations.
NOTE: The dirt pile left on the terrace from the grading work, will be used for filling behind the curb. When this area is landscaped topsoil, grass seed, mulch and matting will be placed over the fill.
Special Needs and/or Disabilities
If you have any special needs and/or disabilities, please email Jeff Bodoh at [email protected] and we will be happy to accommodate in any way possible during the project.