2025 Road Construction Updates – 1-25 Concrete Street Paving Project June 9-13

Andrea Fencl
June 06, 2025

CONSTRUCTION

  • The contractor has finished the sidewalk, driveway apron and landscape work on Ash Grove Place and White Dove Lane.
  • The contractor will be finishing the sidewalk and driveway apron construction on Bear Paw Trail, Snow Goose, Campfire Court and State Street the week of June 9th.  The landscape work will follow shortly after the sidewalk and drive apron work is complete.
  • The contractor is planning to remove soil along the sides and grading Weiler Road, Antelope Trail and Beckett Way the week of June 16th.
  • We are asking homeowners along Weiler Road, Antelope Trail and Beckett Way that have plans to do their own sidewalk to have this work done before June 16th.  We want to avoid conflicts with the street paving work.
  • After the landscaping is finished, we recommend that homeowners water the new landscaping a couple times a week.  This will speed up the growth of the grass, which will prevent weeds from growing.
  • Homeowners can currently park their vehicles on the street in front of their property.  When the contractor is working on the sidewalk work on their street, they will need to park somewhere else between the hours of 7:00 AM and 6:00 PM.
  • The construction schedule may change due to weather or contracts other obligations.

REMINDER – The city recommends that vehicles stay off the new concrete for 7 days after it was poured.  The contractor has been opening driveways earlier then 7 days, but this is their call based on concrete strength testing.