2025 Road Construction Updates – 1-25 Concrete Street Paving Project July 14-18

Andrea Fencl
July 11, 2025

CONSTRUCTION

  • The contractor will finish paving the second lane of Antelope Trail on Monday.  They had another project they had to do on Friday.
  • The contractor will be hand pouring the concrete intersection tie ins at Camp Fire Court, White wolf Lane, and Antelope Trail along Weiler. The contractor will be hand pouring the concrete intersection tie ins at Antelope Trail and White Dove Lane along Beckett Lane.  They will also seal the concrete joints just before opening the streets for traffic.  This work will take place later the week of July 14th.   Antelope Trail might be doing the joint sealing on Monday the 21st .
  • For garbage pick up, please set out your garbage and recycling like usual.
  • The sidewalk and driveway apron work will start once the paving is done on Antelope Trail, Weiler Road and Beckett Lane and the paved streets are open to traffic.
  • The contractor should remove the gravel pile, move the traffic barrels, and grade out the gravel at the intersection of Ash Grove and State Street.  I will remind them about this work.
  • The asphalt paving of the intersection of Ash Grove and State Street will take place in late July or early August.