CONSTRUCTION – Below is the tentative schedule up to the week of May 12. The contractor switched the schedule for 2 streets. Beckett Lane will be moved to Phase 2 which starts in early July. White Dove Lane was added to Phase 1, see schedule below.
- Week of April 28th
- Vinton will continue to grade and trim the gravel to prep for paving – Monday thru Friday
- Pave 1st sides -Tuesday
- Ashgrove Pl-West Side
- Bear Paw Trail-North Side
- Pave 1st sides – Wednesday
- Snow Goose Way-East side
- White Dove Ln- South side
- Campfire Ct-South side
- White Wolf Lane-North Side
- Week of May 5th
- Pave 2nd sides – Friday
- Ashgrove Pl-East Side
- Bear Paw Trail-South Side
- Pave 2nd sides – Friday
- Week of May 12th
- Pave 2nd sides – Monday
- Snow Goose Way-West side
- White Dove Ln- North side
- Campfire Ct-North side
- White Wolf Lane-South Side
- Pave 2nd sides – Monday
- Parking for Phase 1 of the Paving Project
- Weiler Road
- Antelope Trial
- Haas Road
- Beckett Lane
- White Birch Trail
- Hennes Court
- The sidewalk and driveway apron work will start once the paving is done on Phase 1 and the paved streets are open to traffic. The construction schedule may change due to weather or contracts other obligations.
Mail Delivery – The Post Office said that they don’t deliver mail in a construction area. The Post Office said that you can come to the Post Office to pick up your mail. You will need to present an ID at the customer service window to verify your address. They recommend that you pick up your mail in the afternoon. The delivery person should have completed their route and have sorted the current mail. The Post Office is open until 4:45 PM.
This website allows you to sign up for Informed delivery, where you can see what is in your daily mail before it is delivered or you pick it up – Informed Delivery – Mail & Package Notifications | USPS.
Please remember to move your mailbox before construction starts.
Special Needs and/or Disabilities
If you have any special needs and/or disabilities, please email Jeff Bodoh at [email protected] and we will be happy to accommodate in any way possible during the project.